Production of this model was made possible by a generous grant from Union First Market Bank.
Project Progress Reports from:
Jayne Kang | Project Manager, Senior Designer | Machado and Silvetti Associates, LLC
PROGRESS REPORT ITEMS:
Week 3 – Part I: 07/01/13-07/03/13
Material, Assembly and Visual Testing (liner, rainscreen, historic walls, etc)
– North Elevation Full-Assembly Study [continued]
– Typical Armature Corner and Roof Rainscreen Assembly Study
– Test prints of different woods for the site base Model production:
– Final 3/16” ZCorb Print – Final 1/16” ZCorb Prints [Existing(x1)], Proposed (x2)]
– Final modeling adjustments to the armature model for printer
Included in this progress report are digital renderings and photos that document two major efforts made in the course of this short week, which involved:
1) finalizing the quality of material and level of resolution in the site model, with consideration to cost and aesthetics; and

- White oak (second from bottom) was the winner!
2) studies of various isolated assembly details (i.e. mechanical connections, lighting, aesthetic effects when combining the layered elements) in order to come up with something that is clean, most accurately representative, stable and has the best visual effect.
See the first progress report here.